Steel fabrication
Second Static Grizzly at B3 — Fabrication and Installation
Fabrication, assembly and installation of a second static grizzly at the B3 crusher area to support oxide feed to the Kamoto mills.








Project overview
The documented method statement covers fabrication and installation of two static grizzlies at B3, from drawing review and steel cutting through assembly, staging and final installation.
Scope of work
- Review drawings with the client
- Cut structural-steel components to specification
- Assemble and weld the static grizzly structures
- Stage and install at the identified B3 location
- Maintain daily housekeeping and controlled waste disposal
Delivery
The documented fabrication used structural steel, welding and cutting equipment, followed by on-site staging and installation in accordance with the agreed drawings and KCC recommendations.
Safety & environment
The method required daily permits, PPE, risk assessment, authorised personnel, safe material storage, protected openings and orderly work areas.
1 documented locations
Project gallery
Field images are organised by site for clear technical review.
B3 Static Grizzly Fabrication26 distinct documentary photographs.26 media items
Related services
Related projects

Kamoto Copper Company (KCC) · Kolwezi, Lualaba, DRC
Luilu Cobalt Chambers and Plinths Construction
Construction of reinforced concrete plinths (400 × 400 mm) and sewage chambers (6.3 × 3.7 × 2.35 m deep) for the container ablutions at Luilu's Cobalt Plant, with full plumbing and electrical connections (scope EP259-01).
View project
Kamoto Copper Company (KCC) · Kolwezi, Lualaba, DRC
Cobalt Dryer Fencing
Supply and installation of a welded-mesh security fence around the cobalt dryers area at KTC, including 106 steel posts of 3 m set in 1 m deep holes, welded mesh panels, bracing and site demarcation.
View project
Kamoto Copper Company (KCC) · Kolwezi
Acid Plant new ablution chamber
Construction of new ablution chambers at the Acid Plant, documented from reinforcement and concrete placement through blockwork, plastering, cover slabs and completed modular facilities.
View project