Luilu Cobalt Chambers and Plinths Construction

Construction of reinforced concrete plinths (400 × 400 mm) and sewage chambers (6.3 × 3.7 × 2.35 m deep) for the container ablutions at Luilu's Cobalt Plant, with full plumbing and electrical connections (scope EP259-01).

Luilu Cobalt Chambers and Plinths Construction — GNS works

Project overview

Between November 2020 and February 2021, GNS built the ablution infrastructure for the Cobalt Plant area at Luilu: excavation and compaction to 95% MOD AASHTO, 30 MPa reinforced concrete plinths, steps and tank-support slabs, blockwork sewage chambers with Y12 reinforcement, beams, smooth plaster and bitumen waterproofing, and 120 mm concrete lids with steel inspection covers. GNS also supplied and connected the 10,000-litre Jojo water tanks, 220–250 V monophasic pumps and IP65 electrical control panels, and issued the certificate of compliance after testing.

Scope of work

  • Reinforced concrete plinths 400 × 400 mm for container ablutions on three sites
  • Three sewage chambers 6.3 × 3.7 × 2.35 m with blockwork walls and concrete lids
  • 10,000-litre Jojo tanks, pumps and IP65 control panels supplied and connected
  • Plumbing and electrical connections from tanks and pumps to ablutions and chambers
  • Certificate of compliance issued after testing