Building rehabilitation

MV squash court ceiling installation

Rehabilitation of the MV camp squash court (scope EP065-01): new flush-plastered Rhino Board ceiling and full interior and exterior repaint.

Finished MV squash court ceiling by GNS

Project overview

KCC's Engineering Services & Projects department engaged GNS to rehabilitate the deteriorated squash court at the MV camp, covering both the ceiling and the external appearance of the building, scheduled for April 2019.

Scope of work

  • Floor protection with DPC plastic and Masonite
  • Two mobile aluminium scaffold towers
  • Galvanised bracing and Rhino Board ceiling
  • Fibre-taped joints and 3 mm Rhino Lite skim
  • Dulux Weather Guard ceiling paint system
  • Lighting reinstatement
  • Interior, exterior and door repaint

Delivery

The wooden floor was protected with DPC plastic and Masonite sheets. From two mobile 2×2×6 m aluminium scaffold towers, GNS fixed 700 mm galvanised bracing (max. 700×700 mm spacing) to the roof steel with self-tapping screws and installed a flush-plastered Rhino Board ceiling. Joints were fibre-taped, bonding liquid applied and the ceiling skimmed with 3 mm Rhino Lite, then finished with a Dulux Weather Guard primer and two white coats. Lighting was reinstated, old paint stripped, and internal and external walls and the door repainted in Dulux Weather Guard.

Safety & environment

Scaffolding met KCC standards; works followed onsite induction and KCC supervision, with a maintained risk register and housekeeping at all times.