Luilu Lime Plant sewage chambers

Construction of new sewage chambers serving the container ablutions at the Luilu Lime Plant, where no existing sewer network was available.

Luilu Lime Plant sewage chamber construction by GNS

Project overview

Under scope EP025-05, Kamoto Copper Company commissioned GNS to build dedicated sewage chambers for the container ablution facilities at the Luilu Lime Plant. No sewer network existed in the area, so the chambers had to be built as a complete, self-contained structure.

Scope of work

  • Stepped excavation and 200 mm compacted gravel (95 % MOD AASHTO)
  • 35 MPa concrete slab on ref. 617 mesh over 40 m²
  • Columns, block walls and 200×300 mm beams
  • Bituminous waterproofing and smooth plaster
  • Cover slabs with precast manhole frames
  • 110 mm PVC overflow pipework

Delivery

Earthworks: excavation of the pit with walls stepped in 500 mm benches, supply and compaction of a 200 mm gravel layer to 95 % MOD AASHTO. Structure: 200 mm floor slab in 35 MPa concrete on ref. 617 mesh over 40 m², 200×200×2300 mm columns, block walls between columns and 200×300 mm beams, full curing (slab 7 days, walls 3 days), internal bituminous coating, smooth plaster, cover slabs with precast manhole frames and compacted backfill. Plumbing: 110 mm PVC overflow pipes set 1800 mm below the top of the slab.

Safety & environment

Works ran Monday to Friday 07:00–17:00 and Saturday 07:00–12:00 under KCC supervision. KCC provided site access, power and construction water; GNS supplied materials, plant, qualified personnel, PPE and a maintained risk register with mitigation measures.