SKM Engineering eating area

Construction of a designated eating area for SKM Engineering personnel, from demolition of the former structure through masonry, roofing, plumbing, electrical works and finishes.

Completed SKM Engineering eating area built by GNS

Project overview

Under scope EP103-01, requested on 22 January 2019 and scheduled from 1 April to 4 May 2019, GNS constructed a designated lunch area for the SKM Engineering department, which previously had no dedicated eating facility.

Scope of work

  • Demolition and site preparation
  • 200×400 mm concrete-block masonry and plaster
  • 30 MPa reinforced lintels and ring beam
  • 50 mm screed and tiled floor
  • Steel roof structure and green 0.8 mm IBR sheeting
  • Rhino Board ceiling, steel doors and windows
  • Two aluminium double sinks and 50 mm PVC drainage
  • IP65 lighting, power point, switch and extractor fan
  • Complete wall, ceiling and steel paint system

Delivery

The work covered removal and disposal of the existing corrugated roof, purlins, trusses and columns; site clearing; 200×400 mm concrete-block walls with 20 mm smooth plaster; a 50 mm floor screed and tiled finish; 200 mm reinforced 30 MPa concrete lintels and a 100 mm ring beam; a new steel roof structure with green 0.8 mm IBR Chroma deck sheeting; Rhino Board ceiling; steel doors and windows; two aluminium double sinks with water and 50 mm PVC drainage; IP65 lighting, socket, switch, 2.5 mm² wiring and a 300 mm extractor fan; and complete three-coat finishes.

Safety & environment

Work followed KCC site induction, supervision and safety requirements. GNS maintained the risk register, supplied qualified personnel, PPE, materials and equipment, and maintained housekeeping throughout. Working hours were Monday–Friday 07:00–17:00 and Saturday 07:00–12:00.