Fibre optics

Fibre guard wire replacement at Luilu

Replacement of 600 m of defective fibre optic guard wire between the substation and Luilu Dispatch to secure the plant network and instrumentation.

GNS technician on a cherry picker replacing the fibre guard wire at Luilu

Project overview

The aerial fibre linking the substation to the Luilu Dispatch hung on a defective guard wire, exposing the line to falling or breaking and putting the Dispatch and plant instrumentation at risk of outage. KCC engaged GNS to replace it.

Scope of work

  • Removal of 600 m of defective guard wire
  • Installation of 600 m of 25 mm² guard wire
  • Fibre re-fixing onto the new guard wire
  • Repair of defective poles
  • OTDR testing of all network ports

Delivery

GNS removed the 600 m of defective guard wire, installed 600 m of new 25 mm² guard wire, re-secured the fibre onto the new wire and repaired defective poles where required. All network ports were OTDR-tested on completion.

Safety & environment

Work at height was performed from a cherry picker within a 30-day window, on a 7-hour working day and in line with KCC safety policies.