Anyaccess WiFi deployment for KCC
Replacement of KCC's entire existing WiFi system with the Anyaccess FortiAP solution across ten indoor and outdoor points on six operational areas.



Project overview
Requested by KCC's IT department as a network extension, the assignment replaced all current WiFi equipment with Fortinet FortiAP access points under the Anyaccess solution. GNS delivered the full physical deployment on site.
Scope of work
- Access point cabling
- Orange cabinet installation
- Fortinet FortiAP installation — 10 points
- FortiSwitch deployment
- Labelling
- Cabling quality inspection tests
Delivery
GNS ran the cabling for each access point, installed the Orange cabinets, mounted the FortiAP access points, deployed the FortiSwitches and labelled the installation. New FortiAPs were installed at SKM 25 (indoor), SKM 5 (outdoor), Luilu 79 (indoor), Luilu 34 (outdoor), KTO 40 (indoor), KTO 12 (outdoor), KOV 5 (indoor), HQ 3 (indoor), KTC 14 (indoor) and KTC 8 (outdoor). Cabling quality was certified by inspection tests after installation.
Safety & environment
All work followed KCC safety policies and procedures after site safety induction, on a 7-hour working day. KCC supplied the access points, accessories, Orange cabinets and FortiSwitches.
1 documented locations
Project gallery
Field images are organised by site for clear technical review.
Other documented sites3 media items
Related projects

Kamoto Copper Company (KCC) · Kolwezi, Lualaba, DRC
Fiber Network Installation for CCTV — KTO & KTC Stockpile Area
Deployment of single-mode 24-core fiber optic cable and industrial Ethernet for CCTV cameras and servers across the KTO and KTC stockpile areas (project CNTAPP 8025), including roughly 192 splice points, updated AutoCAD network drawings and per-line decibel loss budgets.
View project
Mining site, Kolwezi
CCTV fibre-optic deployment
Pulling, routing and installation of fibre-optic cable for a video-surveillance network across the plant.
View project
Kamoto Copper Company (KCC) · Luilu, Kolwezi
Fibre guard wire replacement at Luilu
Replacement of 600 m of defective fibre optic guard wire between the substation and Luilu Dispatch to secure the plant network and instrumentation.
View project